OG&E Again Asks Regulators To Approve Environmental Plan For Coal Plant

Oklahoma Gas & Electric's coal-fired Sooner Plant in Red Rock, Okla.
Joe Wertz
/
StateImpact Oklahoma

Oklahoma Gas and Electric went before the Oklahoma Corporation Commission again this week to try to get approval for environmental upgrades at its coal-fired power plant in Red Rock, Okla.

The state’s largest utility is running out of time to comply with new federal air quality standards. OG&E’s Sooner Power Plant needs to have air scrubbers installed or be converted to natural gas by January 2019 to comply with the EPA’s Regional Haze Rule.

So far, regulators have twice rejected OG&E’s scrubber plan, which would keep the Sooner units running on coal at a cost of $500 million dollars.

From The Oklahoman‘s Paul Monies:

“This is about preserving fuel diversity,” said Kimber Shoop, an attorney for OG&E. He said OG&E’s plan to install a $500 million scrubber upgrade at the Sooner plant near Red Rock would ensure the utility’s customers get the benefits of low-price coal for another 30 years. The scrubbers are half of OG&E’s “scrub/convert” plan to meet lower sulfur dioxide emissions under regional haze rules. The utility plans to convert two of three coal units at its Muskogee plant to natural gas. OG&E said if it can’t get approval for the Sooner coal scrubber project, it would likely convert the two coal units to natural gas. If regulators grant scrubber approval, the utility would come back after the project is built to add the costs to customer bills.

The new case before the Oklahoma Corporation Commission comes as even more pressure is being put on OG&E to switch the Sooner Plant to natural gas.  Natural gas prices are low, and the industry trend is away from coal and toward cleaner forms of energy.

The case’s other parties — Sierra Club, AARP, Oklahoma Energy Results LLC and Oklahoma Cogeneration LLC — said OG&E’s plan puts too much risk on ratepayers, adding OG&E failed to update economic modeling with new, lower long-term natural gas forecasts. Opponents of the plan said investing money on costly coal scrubbers brings more risks from future environmental regulations.

OG&E says it needs a decision from the commission by early May to get the scrubbers installed in time.


StateImpact Oklahoma is a partnership among Oklahoma’s public radio stations and relies on contributions from readers and listeners to fulfill its mission of public service to Oklahoma and beyond. Donate online.

Logan Layden is a reporter and managing editor for StateImpact Oklahoma. Logan spent six years as a reporter with StateImpact from 2011 to 2017.
More News
Support nonprofit, public service journalism you trust. Give now.