Oklahoma To Offer Incentives To Speed Lexington-Purcell Bridge Repair

J. Stephen Conn
/
Flickr Creative Commons

The Oklahoma Transportation Commission will offer financial incentives to the contractor it chooses to fix a closed bridge between Lexington and Purcell.

The commission has called a special meeting for Friday to award the contract. Commissioners will choose a contractor to perform emergency repairs to the James C. Nance Bridge that was closed Jan. 31 after cracks were found in structural bridge beams.

The project will cost about $5 million. Incentives for early completion and disincentives for finishing late will be up to $2,500 per hour, one of the most aggressive in agency history.

The required bidding process was boiled down from 160 days to only three or four days. It will take an estimated 45 days to complete the repairs and reopen the bridge to car traffic.

VIEW THE AGENDA

-----------------------

KGOU is a community-supported news organization and relies on contributions from readers and listeners to fulfill its mission of public service to Oklahoma and beyond. Donate online, or by contacting our Membership department.

 

The Associated Press is one of the largest and most trusted sources of independent newsgathering, supplying a steady stream of news to its members, international subscribers and commercial customers. AP is neither privately owned nor government-funded; instead, it's a not-for-profit news cooperative owned by its American newspaper and broadcast members.
More News
Support nonprofit, public service journalism you trust. Give now.